Construction of Flyover at Kuril Intersection, Bangladesh
厂辞耻谤肠别:惭叠贰颁 顿补迟别:2019年03月15日

This bridge locates at the “T” intersection of Airport Road and Bishwa Road near Dhaka International Airport. The project includes a flyover with the length of 3,018m, a pedestrian bridge, road works, greening projects, power and lighting projects and underground pipeline relocation and diversion works. The superstructure of the flyover is composed of PC simple supported beam and box girders, while the substructure consists of 750-1,000mm bored piles. It was commenced in April 2010 and completed in May 2012.

Construction of Flyover at Kuril Intersection

 

Print Close